St Ebbes C of E Primary School

Project Overview

The project involved the refurbishment of the pitched roof areas. This included the removal and replacement of roof tiles, battens, and underlay, ensuring materials closely matched the existing roof. A new eaves vent and protection felt were installed, along with dry fixing systems to all verges and the mono ridge.

Project Scope

As part of the works, existing rooflights were removed and replaced with new white-painted pine units, maintaining the original sizes as closely as possible. New flashings and combination kits were installed to match the previous configurations.

During the refurbishment, an insulation upgrade was incorporated, increasing the depth from the originally quoted 100mm to 150mm where possible. Additionally, internal ceiling decorations were carried out in areas affected by the rooflight replacements.

Project Outcome

The project was successfully delivered within the restricted timeframe of the school’s summer holidays. Careful planning and extended working hours were required to meet deadlines, working around the many school programs/clubs.

Related Projects

Lincroft Academy – Phase 2

Construction / Education / Projects

Lincroft Academy – Phase 2
View Project

St Crispin Retirement Village

Construction / Projects / Real Estate

St Crispin Retirement Village
View Project

1-11 Greenfields Close

Pitched roofs / Projects / Roofing

1-11 Greenfields Close
View Project

Request a Call Back

Please note: by completing this form, you accept that M&J Group may contact you from time to time about services which might be of interest to you. You may unsubscribe from these emails at any time and we will never share your information.